Akarana wrote:martync wrote:Yip, it's a full wire that has been run along. They were doing this afternoon, saw then after 2 when I drove by at lunch time.
The electrification crews sure are motoring now!
odaikorob wrote:Akarana wrote:martync wrote:Yip, it's a full wire that has been run along. They were doing this afternoon, saw then after 2 when I drove by at lunch time.
The electrification crews sure are motoring now!
Looks like the last bit of wiring work to be fitted in before Monday 7 Jan, is the stretch from Puhinui to just outside Mitre 10 on the Manukau Branch line. It would be nice to get the wires all the way into the station but I think the load of gantries that have been sitting on the platform there, wont be erected in time. The traction bloke from Taumarunui I spoke to today said that they only do wiring work and that another separate crew do mast erection work beforehand - horse before the cart.
Akarana wrote:odaikorob wrote:Any wiring up at Glen Innes yet?
You won't see any wiring out east until the rest of the lines are mostly completed. They are still busy pouring mast bases and erecting the masts themselves. Orakei Basin will be the one of the last sections as it is, err, most sensitive to the locals.
AKL_Train_Driver wrote:Those gantries must be going outside of the station as there are catenary supports fixed to the underside of the support beams for the trench walls at Manukau. I don't see why they would put them on the platforms... Why not just leave them outside the trench, there is room?
Akarana wrote:martync wrote:Yip, it's a full wire that has been run along. They were doing this afternoon, saw then after 2 when I drove by at lunch time.
The electrification crews sure are motoring now!






















































Chris Randal. wrote:That should push up the hosting costs![]()
![]()
![]()
![]()
![]()
odaikorob wrote:Akarana wrote:martync wrote:Yip, it's a full wire that has been run along. They were doing this afternoon, saw then after 2 when I drove by at lunch time.
The electrification crews sure are motoring now!
Looks like the last bit of wiring work to be fitted in before Monday 7 Jan, is the stretch from Puhinui to just outside Mitre 10 on the Manukau Branch line. It would be nice to get the wires all the way into the station but I think the load of gantries that have been sitting on the platform there, wont be erected in time. The traction bloke from Taumarunui I spoke to today said that they only do wiring work and that another separate crew do mast erection work beforehand - horse before the cart.
john-ston wrote:How long (in metres) is the dock platform?
Matt L wrote:I assume it was designed to allow for at least an SA4 to be docked there. The question though is if we electrify to Puke like it sounds like AT are now planning for it seems that this will be come redundant in a few years.
Matt L wrote:I assume it was designed to allow for at least an SA4 to be docked there. The question though is if we electrify to Puke like it sounds like AT are now planning for it seems that this will be come redundant in a few years.
Return to Auckland Transport Discussion
Users browsing this forum: Google [Bot] and 2 guests